After a trade package is awarded to a subcontractor, the ranking of each bidder will be displayed on PlanetBids under the “Bid Results” tab.
Sub-Tier, Vendors, Suppliers can find contact information for the awarded subcontractor by reviewing the “Prospective Bidders” tab and locating the awarded subcontractor’s contact information.
LABOR COMPLIANCE REQUIREMENTS & FORMS:
The Airport Authority is a Public Agency and therefore requires compliance with the State of California’s Certified Payroll Prevailing Wage Laws.
The Administration Building projects will be using LCP Tracker for monitoring compliance with California Prevailing Wage Law, California Labor Code Sections 1720-1815.
Training workshops will be provided. For dates and times go to EVENTS.
Affidavit of Compliance to be signed by all contractors performing labor on site.
Labor Compliance Documents to be submitted PRIOR to working on site.
Due Dates and Time Frames for required information during construction.
Questions regarding Labor Compliance
Administration Building:
Jacque Hoppes at [email protected] or (619) 321-4845
Liz Deilke at [email protected] or (619) 321-4862
CONSTRUCTION BILLING PAYMENT MANAGEMENT SYSTEM: TEXTURA
- Sundt will invite all Prime Subcontractors to bill through the Textura system
- All Prime Subcontractors must invite their own vendors, suppliers and lower tiers to bill through the Textura system
All prime subcontractors, vendors, suppliers and lower tier-subcontractors should do all billing through Textura to ensure Sundt is aware of your participation on these projects and that all lien releases and utilization reporting is accurate and timely for payment release. Follow prompt payment requirements per Government Code, Section 927, et seq.
SAFETY REQUIREMENTS
Please download and fill out the following Safety Documents
OCIP (Owner Controlled Insurance Program):
The OCIP provides General Liability and Excess Liability coverage (no Workers Compensation) only for work performed at the Project Site by Enrolled Parties.
Enrolled Parties must provide their own insurance for off-site activities and other activities not insured under the OCIP.
Please contact Soula Wynne, Sundt Project Administrator, for a copy of the current OCIP Manual.