Procurement Schedule:
Procurement Packages have all bid out except for BP 11A.
See below for list and Contact Name
Construction On-Going:
McCain Utilities, Building West Foundations thru August 2022
Structural Steel, Metal Decking & Manlift Install Complete November 2022
Structural Concrete and Utility Rough In Complete in December 2022
Building Dry-In Complete February 2023
Exterior Walls and Site Complete Complete June 2023
Project Completion scheduled for February 2024
For Teaming Opportunities with Awarded Prime Contractors
Visit How to Work with Sundt and “View Bid Packages” in PlanetBids for contacts. Once you login to our project specific PlanetBids site (Step #1), select bid results for awarded contractors contact information.
BP 01B – Project Survey – Awarded to NOVA Engineering
Local Goal: 100%
SB/Veteran Goal: 100%
BP 01C – Final Cleaning – Phoenix Cleaning Corps
Local Goal: 0%
SB/Veteran Goal: 100%
BP 01D – SWPPP – Summit Erosion Control
Local Goal: 100%
SB/Veteran Goal: 100%
BP 01E – Testing & Inspection – Awarded to MTGL Engineering
Local Goal: 100%
SB/Veteran Goal: 100%
BP 01G – Manlift – Bigge Crane & Rigging
Local Goal: 5%
SB/Veteran Goal: 0%
BP 02A – Building Trailer Demolition/Removal on McCain Road – Awarded to Pacific Mobile Structures
Local Goal: 100%
SB/Veteran Goal: 0%
BP 3A – Structural Concrete – Awarded to Pacific Southwest Structures
Local Goal: 100%
SB/Veteran Goal: 37%
PSSI Website
BP 03B – Deep Foundation Piles (Design Assist) – Awarded to Condon-Johnson
Local Goal: 100%
SB/Veteran Goal: 18%
Condon Johnson Website
BP 05A – Structural Steel, Metal Decking & Stairs (Design Assist) – Awarded to Cives Steel Company
Local Goal: 0%
SB/Veteran Goal: 24%
BP 05B – Fencing – Sloan Security Group
Local Goal: 0%
SB/Veteran Goal: 0%
BP 05C – Misc. Metals – Bapko Metal
Local Goal: 100%
SB/Veteran Goal: 10%
BP 05D – Bird Deterrent – California Sheet Metal
Local Goal: 100%
SB/Veteran Goal: 100%
BP 06A – Casework – Providence Venture, Inc.
Local Goal: 100%
SB/Veteran Goal: 100%
BP 07A – Roofing & Waterproofing – Courtney
Local Goal: 100%
SB/Veteran Goal: 10%
BP 7B – Metal Panels, Louvers, Sheet Metal, Flashings – California Sheet Metal
Local Goal: 100%
SB/Veteran Goal: 35%
BP 7C – Fire Proofing – GLS Spray Services
Local Goal: 100%
SB/Veteran Goal: 100%
BP 7D – Bird Deterrents – PENDING Award Selection
Local Goal: TBD%
SB/Veteran Goal: TBD%
BP 8A – Doors, Frames, Hardware – Vorwaller & Brooks (Supply) & Union Door Installations
Local Goal: 10%
SB/Veteran Goal: 100%
BP 8B – Glazing – Tower Glass
Local Goal: 100%
SB/Veteran Goal: 17%
BP 8C – Glazing – Elite Glazing
Local Goal: 0%
SB/Veteran Goal: 100%
BP 9A – Metal Framing, Drywall, Insulation – Standard Drywall
Local Goal: 100%
SB/Veteran Goal: 48%
BP 9C – Painting – General Coatings
Local Goal: 100%
SB/Veteran Goal: 0%
BP 9D & 9E – Tile and Flooring – Christian Brothers Flooring
Local Goal: 100%
SB/Veteran Goal: 100%
BP 9F – Terrazzo Flooring – Corridini Corp
Local Goal: 0%
SB/Veteran Goal: 15%
BP 9G – Acoustical Ceiling Tiles – Performance Contracting Inc.
Local Goal: 100%
SB/Veteran Goal: 20%
BP 9H – Access Flooring – Partition Specialties
Local Goal: 0%
SB/Veteran Goal: 0%
BP 10A – Signage – SignAge Identity Systems
Local Goal: 100%
SB/Veteran Goal: 100%
BP 10B – Specialties – PENDING Award Selection
Local Goal: TBD%
SB/Veteran Goal: TBD%
BP 10C – Moveable Walls – L2 Specialties
Local Goal: 0%
SB/Veteran Goal: 100%
BP 11A – Equipment (Kitchen/Consoles/Tables) – Bid Package to be released. Contact Brian Parker
Local Goal: 100%
SB/Veteran Goal: 100%
BP 12A – Window Coverings – Diversified Window Coverings
Local Goal: 100%
SB/Veteran Goal: 100%
BP 12B – Window Washing Equipment – PENDING Award Selection
Local Goal: TBD%
SB/Veteran Goal: TBD%
BP 14A – Elevators – Schindler Elevator
Local Goal: 100%
SB/Veteran Goal: 0%
BP 26A – Electrical (Design/Assist) – Neal Electric
Local Goal: 100%
SB/Veteran Goal: 35%
BP 21A – Fire Protection – Daart Engineering
Local Goal: 0%
SB/Veteran Goal: 100%
BP 22A – Plumbing (Design/Assist) – RL Fick & Son Plumbing
Local Goal: 100%
SB/Veteran Goal: 95%
BP 22B – Gas Line – PENDING Award Selection
Local Goal: TBD%
SB/Veteran Goal: TBD%
BP 23A – HVAC (Design/Assist) – Murray Company
Local Goal: 100%
SB/Veteran Goal: 35%
BP 26B – SDG&E Electrical Ductbank – Morrow Meadows
Local Goal: 100%
SB/Veteran Goal: 0%
BP 26C – Low Voltage – National Electric Works
Local Goal: 100%
SB/Veteran Goal: 0%
BP 26D – Audio Visual – Southland Technology
Local Goal: 100%
SB/Veteran Goal: 100%
BP 26E – Security – ITI Cabling
Local Goal: 100%
SB/Veteran Goal: 100%
BP 31A- Site Demolition + Earthwork – Kyne Construction
Local Goal: 100%
SB/Veteran Goal: 100%
BP 32A- Landscaping & Irrigation – Park West Rescom
Local Goal: 100%
SB/Veteran Goal: 0%
BP 32C + 32D – Site Concrete & Hardscape + Asphalt – Hazard Construction
Local Goal: 100%
SB/Veteran Goal (Site Concrete): 15%
SB/Veteran Goal (Asphalt): 10%
BP 33A – Underground Site Utilities – Kyne Construction
Local Goal: 100%
SB/Veteran Goal: 100%
Project Brief Description
Design-Build Delivery Method: A component of the ADP implementation is replacement of the Authority’s existing administration building. The location of the existing Airport administration building is in conflict with the proposed Terminal and Roadways and Airside Improvements projects such that these projects cannot be completed until the Authority is moved into the new Building and has completed the demolition of the existing administration building. The Authority intends for the Project to be completed as quickly and cost effectively as possible to minimize potential delays to the other Authority projects.Project includes construction of a new four (4) story Building of approximately 130,000 square-feet and relocation of the following existing major functions (key project features) from the current Authority administration building:
- Authority administrative offices;
- Authority Board room;
- Airport innovation lab;
- Authority staff & fleet vehicle parking; and
- Group fitness facility.
State Prevailing Wage and Project Labor Agreements are required.
Local, Small, Veteran Business Participation Goals
Leadership in Energy and Environmental Design (LEED) Silver Certification